Santos happy as GLNG project remains on track for 2015

The GLNG project on Gladstone's Curtis Island is 45% complete.
The GLNG project on Gladstone's Curtis Island is 45% complete.

THE Santos-led GLNG project is now 45% complete and remains on track for first LNG in 2015.

Santos chief executive officer David Knox said construction on the Gladstone project was pleasing.

In Santos' fourth quarter report released on Thursday, Mr Knox said a significant milestone had been achieved for the GLNG underground gas transmission pipeline with the arrival of the last shipment of pipe in Queensland, and the start of pipeline burial.

All 420km of pipe for the gas transmission pipeline has been delivered to pipe yards in Gladstone and Port Alma.

A total of 108km of the mainland pipeline right-of-way has been cleared and graded, with 94km of pipe strung and 35km of pipe welded.

In December, pipeline burial in the Arcadia Valley began, which is the final step before rehabilitation works are carried out, the report said.

For the marine crossing, sealing of the access track started, and site pad and launch shaft preparation is continuing.

A tunnelling machine is being commissioned in Brisbane, and tunnel concrete segment moulds have been prepared. Segment fabrication began in early January.

On Curtis Island, construction of the two LNG trains and supporting infrastructure continues to progress.

Concrete wall lifts are underway for both LNG tanks, erection and welding of the temporary outer support brackets for the steel roof of LNG tank B has been completed and installation of roof plates has begun.

Sanctioned in January 2011, GLNG includes the development of CSG resources in the Bowen and Surat Basins in south-east Queensland, construction of a 420km underground gas transmission pipeline to Gladstone, and two LNG trains with a combined nameplate capacity of 7.8mtpa on Curtis Island.

The project has an estimated gross capital cost of US$18.5 billion from final investment decision to the end of 2015.

Topics:  curtis island, gladstone, glng, lng, mining, resources, santos


Stay Connected

Update your news preferences and get the latest news delivered to your inbox.

Latest deals and offers

Master class from Moneghetti

Steve Moneghetti lived up to his headline billing at the Great Whitehaven Beach Run 10km event on Sunday.

Greens call for change

GREENS Senate candidate Andrew Bartlett stopped into Airlie Beach and met with Dawson Greens candidate Jonathon Dykyj at the early polling booths.

Greens candidates meet in Airlie Beach today.

Set your children a challenge these school holidays

BIG EFFORT: Schoolkids (pictured last year) around the region will again take part again.

Set your children a challenge these school holidays.

Caitlyn Shadbolt, Sara Storer join Gympie Muster bill

Caitlyn Shadbolt performs at CMC Rocks in March 2016.

AWARD-winning singers star in third line-up announcement.

Clive Palmer to re-open refinery

Clive Palmer on ABC radio.

Clive Palmer talks about his achievements, election chances and re-opening the...

Dash Cam of Slip in Snow

Even light snow can be hazardous.

Dash cam shows how easy it is to lose control in even light snow.

Chaos outside Istanbul Airport

Turkish police block the road after an suicide bomb attack at Ataturk Airport in Istanbul, Turkey, 28 June 2016. At least 10 people were killed in two separate explosions that hit Ataturk Airport.

Distress as cars escape Istanbul airport after bombing.

Burnett Heads housing development approved

COUNCIL APPROVED: A Burnett Heads housing development has been approved by Bundaberg Regional Council. Photo Contributed

Councillors approved the development seven votes to four

Three bedroom, 1100sqm block: Is this Qld's cheapest home?

BARGAIN BUY: Is this North Bundaberg property the cheapest home in Queensland?

Becoming a real estate mogul is all about risk and reward